Project information
The scope of work includes the following:
- Installation of the Onshore Pipeline from the offshore Battery Limit to the Receiving Facility at the Integrated Plant. Approximate 25 km Dn 12”
Main Interferences include:
Ten (10) HDD´s for a total approximate length of 5.054 m and two (02) Bored crossings for a total approximate length of 120 m
- Construction, installation, and testing of the Shore Crossing Valve Site and the Receiving Facility including all civil, piping and instrumentation, fencing, lighting, and CCTV.