Participamos en el proyecto «Gas to Energy Project (GTE)», un ambicioso proyecto destinado al suministro de gas natural desde los yacimientos del...
Leer todo
Información sobre el proyecto
The scope of work includes the following:
- Installation of the Onshore Pipeline from the offshore Battery Limit to the Receiving Facility at the Integrated Plant. Approximate 25 km Dn 12”
Main Interferences include:
Ten (10) HDD´s for a total approximate length of 5.054 m and two (02) Bored crossings for a total approximate length of 120 m
- Construction, installation, and testing of the Shore Crossing Valve Site and the Receiving Facility including all civil, piping and instrumentation, fencing, lighting, and CCTV.