Project information
• Clearing of the pipeline right-of-way (ROW), including
temporary work space, and any access required for
clearing and burning activities, loading, hauling
merchantable timber to designated location
• Preparation and development of permanent and/or
temporary access, including grubbing, and bridge and/or culvert installation and/or repair
• Installing, testing and completing reinstatement and
clean-up activities for 54.7 km of NPS 48 pipeline
• Management of novated subcontractors for workforce
accommodations, clearing, security, and medical
scopes, and other services as required
• Installing one pre-fabricated intermediate mainline valve
assembly and two pre-fabricated expeller valve
assemblies, and associated works
• Materials management, such as receipt of the pipe,
fabricated assemblies, and fittings from the Company
designated locations and subsequent hauling to the
ROW
Special works:
Pipeline installation along several steep slopes. No.2 cable crane
systems will be installed and operated to support the pipeline
construction activities along two slopes.