WORLDWIDE EPC SOLUTIONS FOR THE ENERGY INDUSTRY SINCE 1962

WATER TREATMENT AND WATER INJECTION FACILITIES (PHASE 2)

WATER TREATMENT AND WATER INJECTION FACILITIES (PHASE 2)
_("Mappa

Informazioni sul progetto

The project consists of:

  • Produced Water Treatment (Phase 2)
  • LP Water Storage & Distribution Systems expansion
  • Vent Gas Compressor Package
  • New Satellite Instrument House (SIH), control & shutdown, fire & gas system (ICSS).
  • Electrical Power System including substation equipment, switchgear and PMS.
  • Water Injection at WP#4&9 (Phase 2)

CLIENT

LUKOIL (Iraq)

LOCATION

West Qurna 2, Iraq

START OF WORK

2024

END OF WORK

2027