PROJECT | LENGTH | DN" | START | END | |
---|---|---|---|---|---|
ABB (Congo)Construction services for PW1 Project |
2012 | 2013 | |||
ENI CONGO (Congo)EPC contract for M’Boundi Field Development Project related to: Early Phase Water Injection (Work Package PW8.3a); Early Phase Water Injection Network (Work Package PW8.3b); Civil Works for Site Preparation, Flare Installation and Short Term Activities (Work Package PW6) |
PLANT & PIPELINE WORKS | 4“ / 8“ / 12“ / 16“ | 2009 | 2013 | |
FIVES NORDON (France)EPC of the Girland Project, Lussagnet Station |
2,4 Km | VARIOUS | 2012 | 2013 | |
BGE (Ireland)Pipeline to Great Island Power Station, Co. Wexford |
46 Km | 16“ | 2012 | 2013 | |
TIGF (France)EPC of the Girland Project, Pipeline from Lussagnet to Captieux Est |
57 Km | 36“ | 2012 | 2013 | |
ECOPETROL (Colombia)Construction of the Gas Pipeline Cupiagua-Cusiana |
40,2 Km | 18“ / 20“ | 2011 | 2013 | |
TGI (Colombia)Cusiana Project - Lot 2, Construction of a loop of 54km ND 20 between EI Porvenir and Miraflores |
57,2 Km | 20“ | 2011 | 2013 | |
ALLSEAS (UK)Laggan - Tormore Development Project - Installation of Onshore Pipelines & Umbilicals |
12 Km | 30“ / 18“ / 8“ / 2“ | 2011 | 2013 | |
TCO (Kazakhstan)Various Construction Services - Flowlines |
2008 | 2013 | |||
ENAGAS (Spain)Gasoducto Martorell - Figueras Tramo 1 |
84,6 Km | 36“ | 2010 | 2013 |